How long do NYC DOB permits actually take?

Median (p50) and 80th-percentile (p80) days from filing to first permit, per borough and job type — computed from 157,737 DOB NOW filings from the last 24 months. Refreshed weekly from NYC's public DOB NOW dataset. Last computed 2026-07-26.

BoroughJob typeMedian daysp80 daysFilings
Bronx ALT-CO - New Building with Existing Elements to Remain 128 199 105
Bronx Alteration 11 69 12,099
Bronx Alteration CO 82 183 994
Bronx Full Demolition 92 199 492
Bronx New Building 141 262 1,460
Brooklyn ALT-CO - New Building with Existing Elements to Remain 130 241 1,247
Brooklyn Alteration 13 70 32,687
Brooklyn Alteration CO 96 203 2,698
Brooklyn Full Demolition 98 198 730
Brooklyn New Building 147 287 2,120
Manhattan ALT-CO - New Building with Existing Elements to Remain 162 231 68
Manhattan Alteration 15 63 61,114
Manhattan Alteration CO 113 239 1,350
Manhattan Full Demolition 70 232 341
Manhattan New Building 152 296 368
Queens ALT-CO - New Building with Existing Elements to Remain 93 196 918
Queens Alteration 12 67 25,327
Queens Alteration CO 105 207 1,686
Queens Full Demolition 101 189 840
Queens New Building 153 280 1,809
Staten Island ALT-CO - New Building with Existing Elements to Remain 88 212 100
Staten Island Alteration 9 53 6,943
Staten Island Alteration CO 90 203 329
Staten Island Full Demolition 62 119 354
Staten Island New Building 43 141 1,558

Checking one specific job? Use the free permit status lookup. Running permits for clients? PermitBench tracks your whole book against these benchmarks automatically.