How long do NYC DOB permits actually take?

Median (p50) and 80th-percentile (p80) days from filing to first permit, per borough and job type — computed from 157,279 DOB NOW filings from the last 24 months. Refreshed weekly from NYC's public DOB NOW dataset. Last computed 2026-08-30.

BoroughJob typeMedian daysp80 daysFilings
Bronx ALT-CO - New Building with Existing Elements to Remain 127 193 113
Bronx Alteration 11 68 11,910
Bronx Alteration CO 83 193 959
Bronx Full Demolition 93 194 494
Bronx New Building 142 271 1,578
Brooklyn ALT-CO - New Building with Existing Elements to Remain 133 242 1,299
Brooklyn Alteration 13 71 32,491
Brooklyn Alteration CO 98 202 2,738
Brooklyn Full Demolition 99 205 744
Brooklyn New Building 148 287 2,228
Manhattan ALT-CO - New Building with Existing Elements to Remain 160 239 64
Manhattan Alteration 15 64 60,925
Manhattan Alteration CO 114 236 1,380
Manhattan Full Demolition 67 238 366
Manhattan New Building 162 296 393
Queens ALT-CO - New Building with Existing Elements to Remain 96 203 952
Queens Alteration 12 69 24,959
Queens Alteration CO 105 207 1,723
Queens Full Demolition 101 197 863
Queens New Building 152 280 1,876
Staten Island ALT-CO - New Building with Existing Elements to Remain 117 252 106
Staten Island Alteration 9 56 6,811
Staten Island Alteration CO 88 201 337
Staten Island Full Demolition 66 122 345
Staten Island New Building 45 145 1,625

Checking one specific job? Use the free permit status lookup. Running permits for clients? PermitBench tracks your whole book against these benchmarks automatically.