PermitBench

Benchmarks → Staten Island → Alteration CO

Staten Island Alteration CO permits: median 90 days in review

Across 329 Alteration CO filings in Staten Island over the last 24 months, the median time from filing to first permit was 90 days. One in five took longer than 203 days (the 80th percentile).

Job type: Alteration with a new Certificate of Occupancy (Alt-1/Alt-CO). Source: NYC DOB NOW public filings (data.cityofnewyork.us), recomputed weekly. Last computed 2026-07-26.

Alteration CO across the boroughs

BoroughMedian daysp80 daysFilings
Bronx 82183994
Brooklyn 962032,698
Manhattan 1132391,350
Queens 1052071,686
Staten Island 90203329

What this means for your filing

If your Staten Island Alteration CO job has been in review for less than 90 days, it's inside the normal range — pushing DOB now is unlikely to help. Past 203 days, your filing is slower than 80% of comparable jobs and is worth chasing: check for open objections, incomplete items, or a plan-examiner queue issue.

Look up your job number free to see its live status and how it compares — or track your whole client book and get flagged automatically when any permit crosses its borough benchmark.