Benchmarks → Brooklyn → ALT-CO - New Building with Existing Elements to Remain
Brooklyn ALT-CO - New Building with Existing Elements to Remain permits: median 130 days in review
Across 1,247 ALT-CO - New Building with Existing Elements to Remain filings in Brooklyn over the last 24 months, the median time from filing to first permit was 130 days. One in five took longer than 241 days (the 80th percentile).
Job type: Alt-CO — new building with existing elements to remain. Source: NYC DOB NOW public filings (data.cityofnewyork.us), recomputed weekly. Last computed 2026-07-26.
ALT-CO - New Building with Existing Elements to Remain across the boroughs
| Borough | Median days | p80 days | Filings |
|---|---|---|---|
| Bronx | 128 | 199 | 105 |
| Brooklyn | 130 | 241 | 1,247 |
| Manhattan | 162 | 231 | 68 |
| Queens | 93 | 196 | 918 |
| Staten Island | 88 | 212 | 100 |
What this means for your filing
If your Brooklyn ALT-CO - New Building with Existing Elements to Remain job has been in review for less than 130 days, it's inside the normal range — pushing DOB now is unlikely to help. Past 241 days, your filing is slower than 80% of comparable jobs and is worth chasing: check for open objections, incomplete items, or a plan-examiner queue issue.