Benchmarks → Bronx → New Building
Bronx New Building permits: median 141 days in review
Across 1,460 New Building filings in Bronx over the last 24 months, the median time from filing to first permit was 141 days. One in five took longer than 262 days (the 80th percentile).
Job type: New building (NB). Source: NYC DOB NOW public filings (data.cityofnewyork.us), recomputed weekly. Last computed 2026-07-26.
New Building across the boroughs
| Borough | Median days | p80 days | Filings |
|---|---|---|---|
| Bronx | 141 | 262 | 1,460 |
| Brooklyn | 147 | 287 | 2,120 |
| Manhattan | 152 | 296 | 368 |
| Queens | 153 | 280 | 1,809 |
| Staten Island | 43 | 141 | 1,558 |
What this means for your filing
If your Bronx New Building job has been in review for less than 141 days, it's inside the normal range — pushing DOB now is unlikely to help. Past 262 days, your filing is slower than 80% of comparable jobs and is worth chasing: check for open objections, incomplete items, or a plan-examiner queue issue.
Look up your job number free to see its live status and how it compares — or track your whole client book and get flagged automatically when any permit crosses its borough benchmark.