Benchmarks → Manhattan → New Building
Manhattan New Building permits: median 152 days in review
Across 368 New Building filings in Manhattan over the last 24 months, the median time from filing to first permit was 152 days. One in five took longer than 296 days (the 80th percentile).
Job type: New building (NB). Source: NYC DOB NOW public filings (data.cityofnewyork.us), recomputed weekly. Last computed 2026-07-26.
New Building across the boroughs
| Borough | Median days | p80 days | Filings |
|---|---|---|---|
| Bronx | 141 | 262 | 1,460 |
| Brooklyn | 147 | 287 | 2,120 |
| Manhattan | 152 | 296 | 368 |
| Queens | 153 | 280 | 1,809 |
| Staten Island | 43 | 141 | 1,558 |
What this means for your filing
If your Manhattan New Building job has been in review for less than 152 days, it's inside the normal range — pushing DOB now is unlikely to help. Past 296 days, your filing is slower than 80% of comparable jobs and is worth chasing: check for open objections, incomplete items, or a plan-examiner queue issue.
Look up your job number free to see its live status and how it compares — or track your whole client book and get flagged automatically when any permit crosses its borough benchmark.