Staten Island New Building permits: median 43 days in review

Across 1,558 New Building filings in Staten Island over the last 24 months, the median time from filing to first permit was 43 days. One in five took longer than 141 days (the 80th percentile).

Job type: New building (NB). Source: NYC DOB NOW public filings (data.cityofnewyork.us), recomputed weekly. Last computed 2026-07-26.

New Building across the boroughs

BoroughMedian daysp80 daysFilings
Bronx 1412621,460
Brooklyn 1472872,120
Manhattan 152296368
Queens 1532801,809
Staten Island 431411,558

What this means for your filing

If your Staten Island New Building job has been in review for less than 43 days, it's inside the normal range — pushing DOB now is unlikely to help. Past 141 days, your filing is slower than 80% of comparable jobs and is worth chasing: check for open objections, incomplete items, or a plan-examiner queue issue.

Look up your job number free to see its live status and how it compares — or track your whole client book and get flagged automatically when any permit crosses its borough benchmark.