Benchmarks → Manhattan → Full Demolition
Manhattan Full Demolition permits: median 67 days in review
Across 366 Full Demolition filings in Manhattan over the last 24 months, the median time from filing to first permit was 67 days. One in five took longer than 238 days (the 80th percentile).
Job type: Full demolition. Source: NYC DOB NOW public filings (data.cityofnewyork.us), recomputed weekly. Last computed 2026-08-30.
Full Demolition across the boroughs
| Borough | Median days | p80 days | Filings |
|---|---|---|---|
| Bronx | 93 | 194 | 494 |
| Brooklyn | 99 | 205 | 744 |
| Manhattan | 67 | 238 | 366 |
| Queens | 101 | 197 | 863 |
| Staten Island | 66 | 122 | 345 |
What this means for your filing
If your Manhattan Full Demolition job has been in review for less than 67 days, it's inside the normal range — pushing DOB now is unlikely to help. Past 238 days, your filing is slower than 80% of comparable jobs and is worth chasing: check for open objections, incomplete items, or a plan-examiner queue issue.
Look up your job number free to see its live status and how it compares — or track your whole client book and get flagged automatically when any permit crosses its borough benchmark.