PermitBench

Benchmarks → Bronx → Full Demolition

Bronx Full Demolition permits: median 93 days in review

Across 494 Full Demolition filings in Bronx over the last 24 months, the median time from filing to first permit was 93 days. One in five took longer than 194 days (the 80th percentile).

Job type: Full demolition. Source: NYC DOB NOW public filings (data.cityofnewyork.us), recomputed weekly. Last computed 2026-08-30.

Full Demolition across the boroughs

BoroughMedian daysp80 daysFilings
Bronx 93194494
Brooklyn 99205744
Manhattan 67238366
Queens 101197863
Staten Island 66122345

What this means for your filing

If your Bronx Full Demolition job has been in review for less than 93 days, it's inside the normal range — pushing DOB now is unlikely to help. Past 194 days, your filing is slower than 80% of comparable jobs and is worth chasing: check for open objections, incomplete items, or a plan-examiner queue issue.

Look up your job number free to see its live status and how it compares — or track your whole client book and get flagged automatically when any permit crosses its borough benchmark.