Benchmarks → Bronx → Full Demolition
Bronx Full Demolition permits: median 92 days in review
Across 492 Full Demolition filings in Bronx over the last 24 months, the median time from filing to first permit was 92 days. One in five took longer than 199 days (the 80th percentile).
Job type: Full demolition. Source: NYC DOB NOW public filings (data.cityofnewyork.us), recomputed weekly. Last computed 2026-07-26.
Full Demolition across the boroughs
| Borough | Median days | p80 days | Filings |
|---|---|---|---|
| Bronx | 92 | 199 | 492 |
| Brooklyn | 98 | 198 | 730 |
| Manhattan | 70 | 232 | 341 |
| Queens | 101 | 189 | 840 |
| Staten Island | 62 | 119 | 354 |
What this means for your filing
If your Bronx Full Demolition job has been in review for less than 92 days, it's inside the normal range — pushing DOB now is unlikely to help. Past 199 days, your filing is slower than 80% of comparable jobs and is worth chasing: check for open objections, incomplete items, or a plan-examiner queue issue.
Look up your job number free to see its live status and how it compares — or track your whole client book and get flagged automatically when any permit crosses its borough benchmark.